Changes to proposed Road Works Lympne Village

the closure at Stone Street/ Aldington Road is still going ahead from Saturday 1/4 till Monday 17/4 this is for Affinity Water to hand dig to locate there mains , unfortunately the traffic calming cannot be completed at the same time due to time scales with the water .

Walker construction will be submitting a new permit and road closure in the school shutdown summer holidays to build the new table top for traffic calming and Affinity Water can finish there work as well under the same closure , so just for your info the closure will start on Saturday and be off by Monday 17/4 so the schools are free of the works and then return in the summer time